Vidyalelo
Commerce · Q1119

Costing

Graduate and Post Graduate · Commerce · question 1119

Q1119

Which one of the following is not correct with reference to standard costing?

A.
Standard costing is a system where predetermined costs are used for control of entire organisation
B.
Standard may be expressed in quantitative and monetary measures
C.
Only adverse variances are investigated intensively
Answer
D.
Standard is determined for each element of cost

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board