Q43
Which one of the following methods is generally adopted for tunnelling in firm ground
A.
Full face method
B.
Top heading and benching method
C.
Drift method
D.
All the above
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board