Which one of the following questions is relevant to the construction estimates?

A.
Did the estimators precisely evaluate site conditions
B.
Did the estimators use short cut methods which may be unrealistic in their situation
C.
How much money will the contractor's risk, loosing if he were to submit bid on the raw estimate of cost
D.
All of these
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board