Which project required rerouting due to discovery of fault zones?

A.
Sydney Metro
B.
Tokyo Shinkansen Tunnel
C.
London Underground Jubilee Line
D.
Crossrail Project
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
The Crossrail Project in London had to reroute segments when active fault zones and complex urban geology were encountered.