Which type of fault posed a risk to the Taipei 101 Tower construction?

A.
Normal fault
B.
Thrust fault
C.
Strike-slip fault
D.
Blind fault
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
A blind fault (not visible at the surface) near the site posed a seismic risk, requiring specialized design for earthquake resilience.