X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in ?

A.
27 days
B.
36 days
Answer
C.
42 days
D.
18 days

Answer: Option B

Solution

Answer: Option B
Solution:
Time and Work mcq solution image

Time taken by Y alone to complete the total work


Alternate :