16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?

A.
21
B.
28
C.
16
D.
14
Answer

Answer: Option D

Solution

Answer: Option D
Solution: