Q261

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?

A.
10 days
B.
9 days
Answer
C.
12 days
D.
15 days

Answer: Option B

Solution

Answer: Option B
Solution:
L.C.M. of Total Work =60 unit
One day work of A = = 5 unit/day
One day work of B = = 3 unit/day