Q290
A and B can do a job in 10 days and 5 days respectively. They worked together for two days, after which B was replaced by C and the work was finished in the next three days. How long will C alone take to finish 40% of the job?
A.
15 days
B.
18 days
C.
10 days
D.
12 days
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:

Two days work of A and B = 3 × 2 = 6
Remaining work = 10 - 6 = 4
Now as per question
So that 40% of total work done by