A can do 20% of work in 4 days, B can do 331/3\% of the same work in 10 days. They worked together for 9 days. C completed the remaining work in 6 days. B and C together complete 75% of the same work in:
A can do 20% of work in 4 days, B can do of the same work in 10 days. They worked together for 9 days. C completed the remaining work in 6 days. B and C together complete 75% of the same work in:
A.
9 days
B.
15 days
C.
10 days
AnswerD.
12 days
Answer: Option C
Solution
Answer: Option C
Solution:
A = 20 daysB = 30 days

(A + B) × 9 + C × 6 = 60
(3 + 2) × 9 + C × 6 = 60
C = unit
C = = 24 days
(B + C) × x = 60 ×
9x = 90
x = 10 days