Q309
A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work independently. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone?
A.
110 days
B.
118 days
AnswerC.
98 days
D.
120 days
Answer: Option B
Solution
Answer: Option B
Solution: