P and Q together can do a work in 12 days. P alone can do the same work in 36 days. In how many days can Q alone complete two-third part of the same work?

A.
12
Answer
B.
18
C.
21
D.
15

Answer: Option A

Solution

Answer: Option A
Solution:
Time and Work mcq question image
Efficiency of Q = 2
So, required answer =  = 12 days