A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

A.
15 minutes
B.
20.143 minutes
C.
21 minutes
Answer
D.
27 minutes

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board