Vidyalelo
Civil Engineering · all questions

Construction Planning And Management
practice.

Practice every MCQ with options. Use Show answers when you want the correct option and solution.

158

Questions

1/8

Page

Pick an option on a question to see the right answer and solution.

The normal time required for the completion of project in the above problem is

Select an option to see the answer and solution.

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

Select an option to see the answer and solution.

A construction schedule is prepared after collecting

Select an option to see the answer and solution.

If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

Select an option to see the answer and solution.

Bar charts are suitable for

Select an option to see the answer and solution.

The first stage of a construction, is

Select an option to see the answer and solution.

A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

Select an option to see the answer and solution.

The probability of completion of any activity within its expected time is

Select an option to see the answer and solution.

For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is

Select an option to see the answer and solution.

For the network shown in the given figure, the expected time for the activity
Construction Planning and Management mcq question image

Select an option to see the answer and solution.

Time and progress chart of a construction, is also known as

Select an option to see the answer and solution.

The difference between the time avail-to do a job and the time required to do the job, is known as

Select an option to see the answer and solution.

The Overall in-charge of an organization at the site responsible for the execution of the works, is

Select an option to see the answer and solution.

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

Select an option to see the answer and solution.

Various activities of a project, are shown on bar charts by

Select an option to see the answer and solution.

The main disadvantage of line organization, is

Select an option to see the answer and solution.

The main principle of an organization, is

Select an option to see the answer and solution.

A critical ratio scheduling

Select an option to see the answer and solution.

A golden rule for the procurement of construction stones, suggests

Select an option to see the answer and solution.

If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

Select an option to see the answer and solution.