Q341
A is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a task in 15 days. In how many days, will B alone complete 75% of the task?
A.
36
AnswerB.
48
C.
32
D.
44
Answer: Option A
Solution
Answer: Option A
Solution: