Q218
A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?
A.
8 days
B.
10 days
C.
11 days
D.
12 days
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
∴ 3 men and 5 boys will complete the work in 12 days.