P is thrice as good a workman as Q and therefore able to finish a job in 48 days less than Q. Working together, they can do it in ?

A.
18 days
Answer
B.
24 days
C.
30 days
D.
12 days

Answer: Option A

Solution

Answer: Option A
Solution:
Let time taken by P = x days
Then, time taken by Q = 3x days
∴ 3x - x = 48
⇒ 2x = 48
⇒ x = 24
∴ (P + Q)'s 1 day's work

∴ Required time = 18 days
Alternate:
Ratio of times taken by P and Q = 1 : 3
The time difference is 3 - 1 = 2 days
while Q take 3 days and P takes 1 day
If difference of time is 2 days, Q takes 3 days
If difference of time is 48 days,

So, P takes 24 days to do the work.

∴ A and B together can do the work in