Q277
A man does double the work done by a boy in the same time. The number of days that 3 men and 4 boys will take to finish a work which can be done by 10 men in 8 days is ?
A.
4
B.
C.
16
AnswerD.
Answer: Option C
Solution
Answer: Option C
Solution: