P can do 1/4 th of work in 10 days. Q can do 40% of work in 40 days and R can do 1/3 rd of work in 13 days. Who will complete the work first ?

P can do th of work in 10 days. Q can do 40% of work in 40 days and R can do rd of work in 13 days. Who will complete the work first ?
A.
P
B.
Q
C.
R
Answer
D.
Both P and R

Answer: Option C

Solution

Answer: Option C
Solution:
P complete th of work in 10 days
So, P will complete the whole work in 40 days.
Q completes   work in 40 days
Q will complete the whole work in = = 100 days
R completes work in 13 days
R will complete the whole work in = 39 days
Work will be finished firstly by the man who will take less days to complete it,
So, R will complete it first.