A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?

A.
75
B.
100
Answer
C.
125
D.
50

Answer: Option B

Solution

Answer: Option B
Solution:
Let 'n' number of men can required