Vidyalelo
Aptitude · Q178

Time And Work

Competitive Exams · Aptitude · question 178

Q178

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 3/5 part of the work, the number of men he can withdraw so that his work may still be finished in time is ?

A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done part of the work, the number of men he can withdraw so that his work may still be finished in time is ?
A.
45
B.
40
C.
35
D.
30
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
Let 'n' number of men can be withdrawn