Q178
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done 3/5 part of the work, the number of men he can withdraw so that his work may still be finished in time is ?
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done part of the work, the number of men he can withdraw so that his work may still be finished in time is ?
A.
45
B.
40
C.
35
D.
30
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
Let 'n' number of men can be withdrawn