Q2
A mining project is composed of five activities whose three time estimates in months are given below: Activity Estimated duration (months) Optimistic time Most likely time Permissible time 1 - 2 1 1 7 1 - 3 2 5 8 2 - 4 1 1 7 3 - 4 2 5 14 4 - 5 3 6 15 The expected duration of the mining project in months is
A mining project is composed of five activities whose three time estimates in months are given below:
The expected duration of the mining project in months is
| Activity | Estimated duration (months) | ||
| Optimistic time | Most likely time | Permissible time | |
| 1 - 2 | 1 | 1 | 7 |
| 1 - 3 | 2 | 5 | 8 |
| 2 - 4 | 1 | 1 | 7 |
| 3 - 4 | 2 | 5 | 14 |
| 4 - 5 | 3 | 6 | 15 |
A.
5
B.
16
C.
18
AnswerD.
29
Answer: Option C
Solution
Answer: Option C