The failure data analysis of a longwall mining system consisting of thre major subsystems revealed that the failure rate of shearer, face conveyor any stage loader are 0.15/ hour, 0.2/ hour and 0.1/ hour respectively. If all the subsystems must be running for a satisfactory system operation, the reliability of the longwall system for a period of 4 hours is

A.
0.165
Answer
B.
0.259
C.
0.405
D.
0.63

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board