Activity durations in PERT and CPM are decided on the following consideration
A.
PERT - stochastic, CPM - deterministic
AnswerB.
PERT - stochastic, CPM - stochastic
C.
PERT - deterministic, CPM - deterministic
D.
PERT - deterministic, CPM - stochastic
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board