Three jobs A, B and C are to be assigned to three machines X, Y and Z. The processing costs are given below: Machines X Y Z Job A 19 28 31 B 11 17 31 C 12 15 13 The minimum total cost of assigning the jobs to the machines is.

Three jobs A, B and C are to be assigned to three machines X, Y and Z. The processing costs are given below:
Machines
X Y Z
Job A 19 28 31
B 11 17 31
C 12 15 13
The minimum total cost of assigning the jobs to the machines is.
A.
60
B.
54
C.
51
D.
49
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board