Management · Q140

Management Accounting

Graduate and Post Graduate · Management · question 140

Q140

An actual input quantity is 200 units and budgeted input quantity is 50 units, then efficiency variance will be

A.
275 units
B.
250 units
C.
150 units
Answer
D.
650 units

Answer: Option C

Solution

Answer: Option C
Solution:
Efficiency variance = Actual input quantity - Budgeted input quantity
= 200 units - 50 units = 150 units.