Vidyalelo
Management · Q139

Management Accounting

Graduate and Post Graduate · Management · question 139

Q139

If flexible budget variance is 105000, actual cost is 65000 then flexible budget cost will be

A.
$40,000
Answer
B.
$50,000
C.
$150,000
D.
$170,000

Answer: Option A

Solution

Answer: Option A
Solution:
Flexible budget cost = Flexible budget variance - Actual cost
= 65000
= $40000.