Assertion (A): Activity 57 is critical.Reason (R): Earliest finish time and latest finish time for events 57 are same
A.
A is correct but R is not correct
AnswerB.
R is correct but A is not correct
C.
Both A and R is correct
D.
Both A and R is incorrect
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board