Vidyalelo
Civil Engineering · Q58

Tunnel Engineering

Engineering and GATE · Civil Engineering · question 58

Q58

Concrete lining is provided concurrently with the driving operation in case of

A.
Rock terrain
Answer
B.
Soft rock
C.
Running soil
D.
None of these

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board