Q59
In “full face” method of constructing tunnels, the first operation relates to
A.
Removal of bottom portion
B.
Excavation of one drift in the centre
C.
Removal of top portion
D.
Excavation being done along the periphery
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board