Vidyalelo
Civil Engineering · Q81

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 81

Q81

Consider the following operations: 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete The correct sequence of these operations in tunnel construction is

A.
1, 2, 4, 3, 5
B.
1, 3, 2, 4, 5
C.
1, 2, 3, 4, 5
Answer
D.
1, 3, 4, 2, 5

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board