Civil Engineering · Q74

Construction Planning And Management

Engineering and GATE · Civil Engineering · question 74

Q74

Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float

A.
1 and 4 are correct
B.
2 and 3 are correct
Answer
C.
1 and 3 are correct
D.
1 and 2 are correct

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board