Q74
Consider the following statements: In the critical path method of construction planning, Free Float can be. 1. Greater than Total Float. 2. Greater than Independent Float 3. Equal to Total Float. 4. Less than Independent Float
A.
1 and 4 are correct
B.
2 and 3 are correct
AnswerC.
1 and 3 are correct
D.
1 and 2 are correct
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board