Q91
CPM is
A.
Synthesizing in concepts
B.
Is built of activities oriented programmes
C.
Is used for repetitive works
D.
All of the above
AnswerAnswer: Option D
Solution
Answer: Option D
Solution:
CPM is- Synthesizing in concepts
- Is built of activities oriented programmes
- Is used for repetitive works