Vidyalelo
Mechanical Engineering · Q92

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 92

Q92

CPM is the

A.
Time oriented technique
B.
Event oriented technique
C.
Activity oriented technique
Answer
D.
Target oriented technique

Answer: Option C

Solution

Answer: Option C
Solution:
CPM is the Activity oriented technique