Cross regulators in main canals are provided

A.
To regulate water supply in the distributaries
B.
To increase water head upstream when a main canal is running with low supplies
Answer
C.
To overflow excessive flow water
D.
None of these

Answer: Option B

Solution

Answer: Option B