Mining Engineering · Q57

Introduction to Mining Engineering

Engineering and GATE · Mining Engineering · question 57

Q57

Dumper arrives at a shovel at a constant rate of 10 per hour. The service rate is constant at 15 per hour. At a time, the expected number of dumpers in the queue is

A.
2
Answer
B.
3
C.
5
D.
4

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board