Earliest finish time can be calculated as

A.
EST + duration of activity
Answer
B.
EST - duration of activity
C.
LFT + duration of activity
D.
LFT - duration of activity

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board