Q248
The least amount of time an activity is expected to consume. Which one of the following relates to the above expression as per PERT language?
A.
Expected time
B.
Most likely time
C.
Optimistic time
AnswerD.
Pessimistic time
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board