Economic saving of time results by crashing

A.
Cheapest critical activity
Answer
B.
Cheapest noncritical activity
C.
Costliest critical activity
D.
Costliest noncritical activity

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board