For 100 sq. m cement concrete (1 : 2 : 4) 4 cm thick floor, the quantity of cement required, is

A.
0.90 m3
B.
0.94 m3
Answer
C.
0.98 m3
D.
1.00 m3

Answer: Option B

Solution

Answer: Option B