Free float is mainly used to

A.
Identify the activities which can be delayed without affecting the total float of preceding activity
B.
Identify the activities, which can be delayed without affecting the total float of succeeding activity
Answer
C.
Establish priorities
D.
Identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities

Answer: Option B

Solution

Answer: Option B