Q177
If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?
A.
6 days
B.
7 days
AnswerC.
8 days
D.
10 days
Answer: Option B
Solution
Answer: Option B
Solution:
According to the question,4 men = 6 women
2 men = 3 women
10 men + 3 women = 10 men + 2 men
10 men + 3 women = 12 men.....(i)