Q4
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
A.
3.5 and
B.
5 and
C.
3.5 and
AnswerD.
4 and
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board