If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively

A.
3.5 and
B.
5 and
C.
3.5 and
Answer
D.
4 and

Answer: Option C

Solution

Answer: Option C