If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
A.
EF = ES + D
B.
LS = LF - D
C.
LF = LS + D
D.
All the above
AnswerAnswer: Option D
Solution
Answer: Option D