If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be

A.
50 %
B.
Less than 50 %
C.
More than 50 %
Answer
D.
100 %

Answer: Option C

Solution

Answer: Option C