Q147
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
A.
50 %
B.
Less than 50 %
C.
More than 50 %
AnswerD.
100 %
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board