If the toll is to be collected through and outsourced agency by allowing a maximum 10% commission how much amount should be permitted to be collected by the outsourced agency, so that the project is supported with Rs. 4,910 crores?

A.
Rs. 6,213 crores
B.
Rs. 5,827 crores
C.
Rs. 5,401crores
Answer
D.
Rs. 5,316 crores

Answer: Option C

Solution

Answer: Option C
Solution:
Let the amount permitted to be collected = Rs. x