If the value of ore is Rs. 600 per tonne, production cost Rs. 400 per tonne, and cost of overburden removal Rs. 50 per m3, the break-even stripping ratio in m3/tonne is

A.
4 : 1
Answer
B.
3 : 1
C.
1 : 3
D.
1 : 4

Answer: Option A

Solution

Answer: Option A