Q9
In a mine for one shovel six trucks are assigned. The shovel loading time per truck is 5 min, and truck cycle time 20 min. Calculate the match factor.
A.
0.66
B.
1.00
C.
1.20
D.
1.50
AnswerAnswer: Option D
Solution
Answer: Option D
No explanation is given for this question Let's Discuss on Board