Q340
In an underground mine output from the panel is 360 tpd, having 26 days of working in a month where incubation period of coal is 9 month. If recovery from the panel is 80% and pillar size is 30 m × 30 m, height 3 m, coal sp. gravity 1.8 then find out number of pillars in the panel.
A.
18
B.
22
AnswerC.
26
D.
30
Answer: Option B
Solution
Answer: Option B
No explanation is given for this question Let's Discuss on Board