Q312
In costing of project, wages paid to workers for unproductive work at time of material shortage is termed as
A.
indirect wages
B.
health wages
C.
idle time wages
AnswerD.
shortage time wages
Answer: Option C
Solution
Answer: Option C
Solution:
In costing of project, wages paid to workers for unproductive work at time of material shortage is termed as idle time wages. The labour cost of normal idle time may be treated as an item of factory expenses and recovered as an indirect charge in case of indirect workers.